The Mechanics of Paragraph W(11) Deemed Consent
The 56-day deemed approval rule is one of the strongest statutory rights available to developers under English planning law.
Unlike standard planning applications where council delay simply entitles the applicant to lodge a non-determination appeal to the Planning Inspectorate, under Paragraph W(11) of the GPDO:
'The development must not begin before the occurrence of one of the following events: (a) the receipt by the applicant from the local planning authority of a written notice of determination... or (c) the expiry of 56 days following the date on which the application was received by the local planning authority without the authority notifying the applicant as to whether prior approval is given or refused.'
Crucially, in Warren Farm (Whitehall) Ltd v Secretary of State [2019], the High Court confirmed that a decision issued on Day 57 or later is legally void; deemed consent had already crystallised.